Power supply will be disrupted in several areas of Chaukhutia in Almora during October as the electricity department carries out tree-branch trimming near power lines.
The department has issued a date-wise schedule covering areas connected to different feeders. Consumers in the affected locations have been asked to plan essential electrical work before the scheduled interruptions.
Feeder-wise outage schedule
The planned work will take place on the following dates:
- Jaurasi feeder: 12 and 13 October
- Panduwakhal feeder: 14 and 15 October
- Khida feeder: 16 and 22 October
- Dwarahat feeder: 23 and 24 October
- Town feeder: 25 October
- Drinking Water feeder: 26 and 29 October
Electricity supply will remain interrupted in the areas connected to the relevant feeder while the trimming work is under way. The schedule covers separate dates for each feeder, rather than a single interruption across all of Chaukhutia.
Advice for consumers
The electricity department has appealed to consumers to take the scheduled dates into account and finish necessary work beforehand. It has also requested public cooperation during the maintenance programme.
The branch-cutting work is being carried out around electricity lines. The department has not provided further details about the expected duration of each day’s interruption in the available information.
Conclusion
Residents in the listed Chaukhutia feeder areas should check the date-wise programme, complete essential work in advance and plan for interruptions during the scheduled tree-trimming operations.
Frequently Asked Questions
Q. Why will electricity supply be interrupted in Chaukhutia?
Electricity lines are being maintained through the trimming of tree branches around them.
Q. Which area will face disruption on 12 and 13 October?
The disruption is scheduled for areas connected to the Jaurasi feeder.
Q. When will the Panduwakhal feeder be affected?
Work is scheduled on 14 and 15 October for areas connected to the Panduwakhal feeder.
Q. Which dates are listed for the Khida feeder?
The Khida feeder areas are scheduled for work on 16 and 22 October.
Q. When will the Dwarahat feeder supply be interrupted?
The Dwarahat feeder is scheduled for work on 23 and 24 October.
Q. When are the Town and Drinking Water feeders scheduled?
The Town feeder is scheduled for 25 October. The Drinking Water feeder is scheduled for 26 and 29 October.
Q. What has the electricity department asked consumers to do?
Consumers have been asked to complete essential work in advance and cooperate during the scheduled operations.